Staff Housing Project – Construction Progress Update
                
                Posted Date: 11/02/25 (12:07 PM)
            
            
            
Inside the buildings, work on the mechanical, electrical, and plumbing systems will take place from mid-November through early December as well. The design and construction team—Ausonio Inc., 19six Architects, and Education Housing Partners, and the District—continues to meet weekly to coordinate progress, review building materials, and finalize finish selections for the new homes.
On November 12, the District will host a “Box Walk,” where district staff and project partners to will tour the first completed one- and two-bedroom framed units. This milestone represents an step forward as we continue transforming this long-awaited project from concept to reality.
The District appreciates the ongoing support of our community, city partners, and staff as we work together to bring quality, affordable housing options to Soledad educators and staff.
We have included some pictures showing the progress on the project.
Installation of the 2nd floor joists began on Friday, October 31
The fence has been completed.
The parking lot grading is underway.
Thanks to the Soledad Community for their support!
                        
                        